Project Update

Jeffrey Grade Separation Project Update

The City of Irvine is nearing completion of the Jeffrey Road Grade Separation project, which provides a railroad bridge at the existing Metrolink railroad tracks to allow traffic to move freely under it. The project is one of the largest and most complex Public Works projects ever undertaken by the City.  

The project has been constructed in five phases:

Phase 1

  • Construct a lighted, four-lane detour road

 

Complete

  • Construct a train track detour

 

Complete

  • Install a noise/dust barrier at The Meadows Mobile Home Community

 

Complete

  • Install a pump station (building) for ground water disposal

 

Complete

  • Transition traffic to the detour road

 

Complete

  • Relocate utilities

 

Complete

Phase 2

  • Transition train traffic to the track detour

 

Complete

  • Widen Jeffrey (three lanes in each direction)

 

Complete

  • Construct the pedestrian overcrossing

 

Complete

  • Install mechanical/electrical equipment in the pump station

 

Complete

  • Construct the retaining walls (1 & 2)

 

Complete

  • Continue to relocate utilities

 

Complete 

Phase 3

  • Construct the railroad bridge (Phase I)

 

Complete

  • Transition train traffic to the new railroad bridge

 

Complete

  • Continue to construct the retaining walls (4 & 5) 

 

Complete

  • Continue to relocate utilities

 

Complete

Phase 4

  • Remove the train track detour

 

Complete

  • Excavate Jeffrey under train track detour

 

Complete

  • Complete the railroad bridge (Phase II)

 

     Complete

  • Complete utility relocations

 

     Complete

  • Complete the retaining walls (3 & 6)

 

Complete

  • Complete Jeffrey street improvements

 

     Underway

Phase 5

  • Transition traffic to the new Jeffrey

 

      Complete

  • Remove the four-lane detour road

 

      Complete

  • Complete maintenance roads, bicycle paths, and landscaping

 

      Underway

The target completion date for the project is April 2011.

To mitigate construction-related impacts on traffic, construction begins after 7 a.m. and ends at 3:30 p.m.  All traffic lanes remain open, however, before 9 a.m. and after 3 p.m.

Safety First


During construction, the safety of both the public and the workers is the City’s top priority.  To this end, the Irvine Police Department is enforcing a 35 mph speed limit within the project construction zone. Please help us by adhering to the posted speed limit. 

For your safety, bicycle lanes and the bicycle trail on Jeffrey and along the Metrolink railroad have been closed for the duration of the project. Bicycle detour signs are posted on surrounding streets including Irvine Center Drive, Walnut, Sand Canyon, and Yale.

We ask that, for your own safety, you stay away from the construction site at all times – even when workers are not present.

For additional information about the Jeffrey Road Grade Separation Project, please contact: